Decarbonize! (presentation, 2026-06-08) opposes Kilshane Energy’s proposed 680 MW Dublin peaker and argues for replacing peaking gas with grid‑scale batteries. The video compares costs, flexibility, and emissions, cites California and Australia battery growth and Aliso Canyon lessons, highlights stranded‑asset risk, and notes planners refused permission for the plant.

Why it matters

Kilshane Energy lodged plans for a 680 MW gas peaker power plant in Dublin (Pleanála case 323897); planners later refused permission, and the proposal would have locked Ireland into decades of fossil‑fuel peaking capacity and fuel dependence.

Key details

  • Grid‑scale batteries are presented as a cleaner, cheaper, and more flexible alternative for peak balancing: evidence cited includes rapid growth of California’s battery fleet through 2025, Australia’s big batteries overtaking peaking gas on the main grid, and the Aliso Canyon (2015) disaster as a cautionary example.
Source evidence

Kilshane Energy proposes building a 680 MW gas peaker power plant in Dublin, Ireland. However, grid-scale batteries offer a cleaner, cheaper, and more flexible alternative for balancing the grid during peak demand. Building the gas plant would lock Ireland into decades of pollution and fuel dependence, while batteries could enable a modern, renewable-powered grid.

If you'd like to support my work, you can buy me a beverage
https://www.buymeacoffee.com/Decarbonize

https://www.pleanala.ie/en-ie/case/323897

10 years since Aliso Canyon: Disaster was wake-up call for U.S. on dangers of underground gas
https://www.latimes.com/environment/story/2025-10-23/aliso-canyon-10th-anniversary

Chart: The remarkable rise of California’s grid battery capacity
https://www.canarymedia.com/articles/batteries/chart-the-remarkable-rise-of-californias-grid-battery-capacity

California’s Battery Storage Fleet Continues Record Growth, Strengthening Grid Reliability
https://www.energy.ca.gov/news/2025-11/californias-battery-storage-fleet-continues-record-growth-strengthening-grid

Kilshane Energy lodges plans for 680mw Dublin power plant
https://www.rte.ie/news/business/2026/0602/1576453-kilshane-energy-dublin-power-plant/

Big batteries overtake peaking gas generators on Australia’s main grid for first time
https://reneweconomy.com.au/big-batteries-overtake-peaking-gas-generators-on-australias-main-grid-for-first-time/

The role for open cycle gas turbines in Ireland’s renewables drive
https://www.pinsentmasons.com/out-law/analysis/the-role-open-cycle-gas-turbines-irelands-renewables-drive

Planners refuse permission for Kilshane power plant
https://www.irishtimes.com/business/energy-and-resources/planners-refuse-permission-for-kilshane-power-plant-1.4806104

Out of gas: Managing the decline of gas in Australia
https://grattan.edu.au/report/out-of-gas-managing-the-decline-of-gas-in-australia/#waypoint=chapter-5-finance-and-plan-gas-powered-generation-differently
https://www.semopx.com/market-data/market-results

Gas Networks Ireland selects the Shannon Estuary as location for the Strategic Gas Emergency Reserve
https://www.gasnetworks.ie/corporate/news/active-news-articles/shannon-estuary-location

Keep Ireland LNG Free - No new fossil fuel infrastructure in a Climate Crisis.
https://my.uplift.ie/petitions/keep-ireland-lng-free

Keep Ireland LNG Free
https://notherenotanywhere.com/wp-content/uploads/2025/06/NHNA_LNG-Short-Briefing-Doc.pdf-2.pdf

Timestamps
No new fossil fuel infrastructure 0.00
Why peaker plants were needed 0:39
What is a peaker plant 1:19
Moving from peakers to batteries 3:07
Stranded assets 6:33
Do we want a 20th century grid in the 21st century 7:14

Channel: Decarbonize!
Published: 2026-06-08
Video URL: https://www.youtube.com/watch?v=io4RjLu5cyw